PPAP Sample Size

  • As specified in the AIAG Manual (Section 2), PPAP shall be taken from a significant production run.
  • “Parts from each unique production process, e.g., duplicate assembly line and/or work cell, each position
  • of a multiple cavity die, mold, tool or pattern, shall be measured and representative of parts tested.”
  • This applies to all shifts, production lines and locations producing parts for DTNA.
  • Suppliers are required to submit PPAP documentation according to the following table:

If there is inability to provide the required sample size, please contact you Supplier Quality Engineer through the PPAP System using the corresponding PPAP ID.

Estimated Annual Usage (EAU). From:Estimated Annual Usage (EAU). ToQuantity of parts to
be submitted on
PPAP Dimensional
Report
001
1121
13241
25362
37483
49604
611205
12124010
24150020
50110,00030