PPAP Due Dates

  • Do not wait until the due date to submit the PPAP, submit the PPAP as soon as it is completed
  • The due date of the PPAP depends on a few factors
  • If the PPAP is tied to a tooling PO, the tooling due date is the PPAP due date
    • You can check this by checking the PPAP request and looking to see if there is a tooling PO assigned
    • A source of RRRC will mean the PPAP is tied to tooling
      • To adjust these due dates, you will need to use the tooling dashboard
  • PPAPs with a source of Corporate or Resource the due date will be tied to the changeover or pre series date.
    • Corporate or Resource PPAPs can have a tooling PO, verify if they have one before taking further steps to attempt to change the date.
  • Non tooling corporate or resource PPAPs will have a due date that is set 4 weeks prior to the changeover or pre series date, whichever is soonest.
    • DTNA launch and change management controls these dates
  • PPAPs with a QE or PPCN listed as the source, the due dates are set by the DTNA QE.
    • These PPAPs are usually created for a specific reason most commonly from a PPCN that has been submitted.
    • The due date will be set to the date that is listed on the PPCN form
      • If the change is taking longer than anticipated, you will need to contact your QE by sending a comment in the PPAP system.
What are the 5 possible PPAP sources?

Corporate, Resource, RRRC, QE, or PPCN